Cornbrook Metrolink tracks get a 27C 'stress' to prepare for extremes

Four kilometres of track are being replaced near one of the network’s busiest junctions, with the work intended to improve safety and lift speed restrictions.

Cornbrook Metrolink tracks get a 27C 'stress' to prepare for extremes – Manchester Ethan Sarkar

At Cornbrook in Manchester, Metrolink track is being replaced along a four-kilometre stretch, with the rails heated as part of a process designed to make them behave as if they are always at 27 degrees. The renewal is intended to prepare the network for decades of use.

The work is being carried out in three stages to break up disruption. Stage two was nearing completion on 1 November after two weeks without trams on the Altrincham, Trafford Centre and Eccles lines. Passengers have reported crowded replacement buses, cancellations and waits of up to 40 minutes.

Cornbrook is a busy junction, with trams passing every 30 seconds for 20 hours a day, seven days a week, when all lines are open. Transport for Greater Manchester network director Ian Davies said the old rails were reaching the end of their 30-year life. TfGM says replacing them will improve safety and could allow speed restrictions to be lifted, saving up to 60 seconds on journeys compared with timings before the works.

Why the rails are heated

The job involves removing the existing track, excavating to formation level, laying ballast and sleepers, then fitting and aligning the new rails. Around 620 metres of drainage has also been installed to prevent water collecting along the line.

Rails expand in heat and contract in cold. If temperatures fall too far, a rail can snap; if they rise too high, it can buckle. Stressing the metal by inducing heat is intended to increase its resilience when outdoor temperatures change. The rails arrive in 18-metre lengths, each weighing about 900kg. Sleepers weigh between 250kg and 300kg.

What happens next

TfGM has brought in specialist machinery to lift track sections into place, level the ground and fit the clips that secure the rails. The equipment can install four clips for every one fitted by hand. Project leaders estimate the machinery has saved a couple of weeks compared with doing the work without it.

The current stage was described as nearing completion, but a precise end date for the disruption is not stated. The timetable for the third stage has also not been given.

This report draws on information from Manchester Evening News.